Chiller Operation and Maintenance

Chiller Operation , Purpose Chiller Operation, The purpose of this SOP is to define the operation and maintenance procedure of Chillers of XX Pharmaceuticals Ltd. Chiller Operation , Scope This SOP applies to the Chillers manufactured by Trane, USA which is located at the roof top area of Sterile and Sterile blocks of XX Pharmaceuticals […]


Chiller Operation , Purpose

Chiller Operation, The purpose of this SOP is to define the operation and maintenance procedure of Chillers of XX Pharmaceuticals Ltd.

Chiller Operation , Scope

This SOP applies to the Chillers manufactured by Trane, USA which is located at the roof top area of Sterile and Sterile blocks of XX Pharmaceuticals Ltd.

Definitions / Abbreviation:

[][]EHS: Environment Health and Safety.
[][]PPE: Personal Protective Equipment.
[][]SOP: Standard Operating Procedure.
[][]AHU: Air Handling Unit.

Responsibilities:

[][]The roles and responsibilities are as follows

Engineering ( Validation) Department

[][]To prepare the SOP & revise it when necessary.

Engineering (Maintenance) Department

[][]To provide necessary support for smooth operation & maintenance of chillers.
[][]To ensure that the operators are responsible to carry out the operation and maintenance work and regular checking of the critical components and logbooks.
[][]To engage technician/mechanic/operator/supplier in repair and maintenance work.

Operators/Technician

[][]To operate the chiller according to the SOP.
[][]To fill up the logbooks related to the Chiller.
[][]To do the maintenance job according to the schedule.

Head of Engineering

[][]To ensure that the operation and maintenance of Chiller are done properly.
[][]To approve any maintenance/plans related to the Chiller.

Head of Quality Assurance

[][]To approve this SOP
[][]To ensure overall implementation of this SOP.

Procedure

Precautions:

[][]All maintenance work must be carried out safely in accordance with the requirements of the Plant Safety Requirements and the EHS safety notices must be displayed around the plant. [][]Specific attention must be paid to the following:
[][]Personal protective equipment (PPE) and clothing appropriate to the job must be worn.
[][]Equipment must be electrically isolated and locked out where possible.
[][]Ensure the control panel is switched off before carrying out any check.
[][]Maintenance activity must be carried out by trained technician/operators.
[][]“Under Maintenance” tag must be put while doing maintenance tasks.

System Description:

[][]Chiller is used to produce chilled water which is used in AHU’s cooling coil to cool the air. There are two chillers at the roof top area of Cephalosporin block and two at the roof top area of General Block. Each chiller has capacity of 250 Ton.
[][]The chiller works according to the Vapor Compression Refrigeration Cycle. There is an evaporator (heat exchanger) to chill the water by exchanging heat with the refrigerant. The refrigerant used in this system is R134a.

[][] The vapor refrigerant from the evaporator is sucked into the compressor and compressed to a higher pressure. There is a water cooled condenser to cool the refrigerant. The flow of refrigerant is controlled by using an expansion valve before entering into the evaporator.

Pre-Start Check:

[][]Check the power supply voltage within the utilization range.
[][]Verify that all refrigerant valves are “OPEN”.
[][]Check the chilled water.
[][]Check the Condenser water.
[][]Check cooling Tower water level.
[][]Check the fused-disconnect switch (es) that supplies power to the chilled water pump starter and the condenser water pump starter.
[][]Check all piping for leakage.
[][]Check the chilled water and condense water valve are “OPEN”.
[][]Visually inspect the chilled water pressure and condenser water pressure.
[][]Check the voltage of chiller.

Starting procedure:

[][]Following steps are followed to start the chillers
[][]Turn chiller circuit breaker (Panel Board) handle to “ON” Position.
[][]Start the chilled water pump
[][]Start Condenser water pump.
[][]Check the evaporator water flow.
[][]Check the condenser water flow.
[][]Start the cooling tower fan.
[][]After 10-30 Seconds Figure-I will be displayed.
[][]For checking condenser and evaporator circulating water we have to go to report option and check water flow.
[][]Touch the Report key and check water flow for condenser and chilled water circulating pump and oil temperature (Figure-II).
[][]After checking water flow, check the Setting of parameters.
[][]For setting parameter touch the” Setting” Key. Figure-III.
[][]Go back to Main screen menu and then touch the’ AUTO” key.
[][]After pressing the “AUTO” Figure-IV is displayed.

During Operation:

[][]Fill up the operational log book of chillers while the chillers are running on every 2 hours.

Stopping Procedure:

[][]At first Unlock the screen
[][]Touch the “STOP’’ key on screen.
[][]After stopping the chiller 5-10 minutes later
[][]Stop the condenser water pump.
[][]Stop chilled water circulating pump.
[][]Stop Cooling Tower Fan.

Chiller Preventive Maintenance Procedure:

[][]Use of a periodic maintenance program is important to ensure the best possible unit performance and efficiency.
[][]Fill up the maintenance log sheet of Chillers after doing maintenance.

Daily Maintenance

[][]Check the chiller’s evaporator and condenser pressures, and discharge oil pressure.
[][]Check the oil level in the chiller oil sump.
[][]Clean the chiller outside and surroundings.
[][]Check setting and operation of all controls and safety devices.

Weekly Maintenance

[][]Clean the environment of chiller room.
[][]Clean outside of the chillers, chilled water pumps.
[][]Clean outside of the condenser water pump.
[][]Check the electrical connection.

Monthly Maintenance

[][]Clean all water strainers in both the chilled and condensing water piping system.
[][]Measure the oil pressure drop. Replace oil filter if required.
[][]If operating conditions indicate a refrigerant shortage, leak checks the unit and confirm using soap bubbles.
[][]Repair all leaks.
[][]Check the motor bearing.
[][]Grease all pumps.

Annually Maintenance

[][]Check all isolators of pumps.
[][]Check starter contactors for wear and replace if required.
[][]Check motor winding insulation.
[][]Check motor amps draw.
[][]Clean condenser tubes.
[][]Check water pipeline for any leakage.
[][]Change the chilled water, refill with chemical.
[][]Change the condenser water.
[][]Check the evaporator and condenser flow switches.

Annexure

Annexure-I: Operational log sheet of Chillers
Annexure-II: Maintenance log sheet of Chillers


1 thought on “Chiller Operation and Maintenance”

  1. Bill

    I found this article very helpful. All of the content of this site, I read was pretty awesome. Hope this will hep to others.

Leave a Comment

Your email address will not be published. Required fields are marked *

error: Content is protected by www.pharmaguideline.co.uk !!