ROPP Cap Sealing Machine Set Up, Operation & Cleaning

ROPP Cap Sealing Machine, Purpose : ROPP Cap Sealing Machine, The purpose of this SOP is to describe the Operation and cleaning procedure of ROPP Cap Sealing Machine (Model: PPM-35) in order to comply with cGMP standard. ROPP Cap Sealing Machine, Scope : The scope of the procedure is applicable to the ROPP Cap Sealing […]


ROPP Cap Sealing Machine, Purpose :

ROPP Cap Sealing Machine, The purpose of this SOP is to describe the Operation and cleaning procedure of ROPP Cap Sealing Machine (Model: PPM-35) in order to comply with cGMP standard.

ROPP Cap Sealing Machine, Scope :

The scope of the procedure is applicable to the ROPP Cap Sealing Machine (Model: PPM-35) at the Production area of XX Pharmaceuticals Limited.

Definitions / Abbreviation:

N/A.

Responsibilities:

[][]The Roles and Responsibilities are as follows:

Operator

[][]Setting, operation and cleaning of the Cap Sealing Machine (Model: PPM-35)
[][]Maintaining Equipment Log Book.

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly

Manager, Quality Assurance

[][]To approve the Document

Procedure:

Precaution:

[][]Ensure that area & equipment are clean and suitable to start the operation.
[][]Use protective suit, surgical gloves, head gear, cotton mask, and safety goggles during sealing operation.
[][]In case of emergency, press the emergency switch to stop the machine.

Machine Assembling

[][]Set the base of the machine by specific nut and attach the bottle adjuster.
[][]Set the sealing wheel according to the neck diameter of the bottle.
[][]Fix the bottle size by moving the base.

Machine Operation

[][]Load the bottle on the SS table.
[][]Fix the plastic stopper and aluminum cap on the empty bottle.
[][]Turn on the main switch of the machine.
[][]Take a bottle on the base.
[][]Seal it by the moving sealing wheel.
[][]Check the leakage by leak test apparatus.
[][]If sealing is accurate then another eight empty bottle have to seal.
[][]Take them again for leak test.
[][]Continue the sealing operation if sealing is accurate.
[][]Turn off the all switch gradually after complete the sealing operation.
[][]Record the machine start & end time and other parameters in the ‘Equipment Log Book’

Machine Dismantling

[][]Turn the main switch off.
[][]Dismantle the parts like moving sealing wheel, bottle adjuster unit and transfer them to the wash bay.

Machine cleaning

[][]Remove dusts from the machine with a vacuum cleaner. Collect dust from machine body.
[][]Clean all the machine parts with dry lint free cloth.
[][]Use potable water to clean the machine body and holding screw.
[][]Use hot water to clean all the product contact parts & finally rinse with purified water.
[][]Clean and swab all the parts with lint free cloth to remove water.
[][]After final cleaning affix the ‘CLEANED’ label.
[][]Record the cleaning parameters on the ‘Equipment Log Book’.