Water Handling System at the Production Premises

Water Handling System, Purpose: Water Handling System, To lay down the procedure of Water handling system at the Production premises. Water Handling System, Scope: This SOP is applicable for the Production Area of XX Pharmaceuticals Limited. Definition / Abbreviation: [][]N/A Responsibilities: [][]The Roles and Responsibilities are as follows : Operator [][]To follow the laid down […]


Water Handling System, Purpose:

Water Handling System, To lay down the procedure of Water handling system at the Production premises.

Water Handling System, Scope:

This SOP is applicable for the Production Area of XX Pharmaceuticals Limited.

Definition / Abbreviation:

[][]N/A

Responsibilities:

[][]The Roles and Responsibilities are as follows :

Operator

[][]To follow the laid down procedure.

Executive, Production

[][]To monitor and check the laid down procedure.

Manager, Production

[][]To implement this correctly.

Head of Quality Assurance

[][]To approve the Document.

Annexure:

[][]N/A

Procedure:

Precaution :

[][]During collection of hot water, wear heat resistance gloves.
[][]Before collection check all the point of connection & ensure that no one is open.
[][]Keep all inlet and outlet of circulating loop / storage tank and open ends of S.S. pipelines closed at the day end of work
[][]Always keep the water off-take valves closed at every use point after use.
[][]At the end of the day, ensure that no flexible hose pipe remains attached with the use point.
[][]Potable water should not be use in manufacturing process.

Types :

[][]Three types of water used in Manufacturing area.
Potable Water
Hot Water
Purified Water
Potable Water
[][]Connect pipe with the potable water system.
[][]Check availability of potable water in the line.
[][]Collect potable water from potable water mark water line.
[][]Use Pharma grade container to collect potable water for cleaning purpose.
[][]Transfer potable water to the respective production area by using SS trolley.
[][]After completion of work hang the pipe on the hanger.
[][]Keep both ends close with Alu foil after drain out of remaining water from pipe at the end of the day work.

Hot Water

[][]Connect pipe with the hot water system.
[][]Check availability of hot water in the line.
[][]Collect hot water from hot water mark water line.
[][]Use Pharma grade container to collect hot water for cleaning purpose.
[][]Transfer hot water to the respective production area by using SS trolley.

Purified Water

[][]Before Collection of purified water from the main re-circulation loop of purified water, connect the pipe with 50 Liter storage tank and main loop.
[][]Collect the purified water into the storage tank by turning the valve open.
[][]Circulate the water through the sectional circulation loop for 5 minutes and drain through use points and storage tank outlet.
[][]Transfer purified water to the respective production area by using SS trolley.
[][]After completion of work, disconnect the pipe between the pipe storage tank and main circulating loop and hang the pipe on the hanger.
[][]Keep both ends close with Alu foil after drain out of remaining water from pipe at the end of the day work